Skip to content
Independent · Sourced
← All individuals
Kinga Surma

Kinga Surma

MPP for Etobicoke Centre: voting record

Instigator

Estimated cost to Ontario

$500.0M

Ontario Minister of Infrastructure. On June 21, 2024, Surma announced the immediate closure of the Ontario Science Centre, attributing it to a Rimkus engineering report about distressed roof panels. FOI documents subsequently revealed that draft versions of the same Rimkus report from March, April, and May 2024 had recommended routine maintenance — not closure — and that Infrastructure Ontario was in "frequent communication" with Rimkus in the lead-up to the final report. The Auditor General had already found the original relocation decision was based on "preliminary and incomplete costing information."

Connected scandals

  • Ford abruptly closed the Ontario Science Centre on June 21, 2024, citing a dangerous roof — but the engineers' own report did not recommend closure. The same roofing material exists in 400+ other Ontario buildings that remain open. The roof survived a major snowstorm intact. Ford refused to reopen it anyway. The Science Centre is now temporarily housed in a mall and at Harbourfront while a replacement is built at Ontario Place — a project whose cost has ballooned from $322 million to over $1 billion, with the new building 45% the size of the original.

    Made the public announcement closing the Science Centre with two days' ministerial notice, citing an engineering report that earlier drafts had not used to justify closure. Global News reported Infrastructure Ontario coordinated extensively with the engineering firm before the final report was issued. The closure enabled the government to proceed with its plan to relocate the Science Centre to Ontario Place as part of the Therme redevelopment.

  • To prepare Ontario Place for a private Austrian spa, the Ford government rerouted a raw sewage overflow pipe into the West Channel of Lake Ontario — bypassing public consultation, exempting the project from environmental review, and proceeding over the objections of physicians, landscape architects, and 2,250 Ontarians who formally opposed the plan.

    As Minister of Infrastructure, Surma oversaw Infrastructure Ontario's management of the Ontario Place redevelopment, including the construction of the combined sewer overflow reroute into the West Channel that began December 1, 2025. Infrastructure Ontario notified City of Toronto staff directly of the construction start.

  • Ford's Bill 98 strips Toronto and the TTC Board of all authority over fares, service standards, and transit governance — handing the Minister of Transportation unchecked power to set prices, zones, and routes for the first time in over a century. Transit workers, riders, city council, and even TTC management are unanimous in opposition, but Ford's majority means the bill will pass.

    As Ontario's Minister of Infrastructure, Surma co-announced Bill 98 alongside Transportation Minister Prabmeet Sarkaria on March 30, 2026. The bill's transit takeover provisions are framed as infrastructure integration but grant the province sweeping unilateral control over TTC fares, service standards, and route operations.

  • Doug Ford signed a $100-million Starlink broadband deal to appeal to Trump's inner circle, then abruptly cancelled it in response to Trump's tariffs. He then negotiated a confidential settlement to pay Elon Musk an undisclosed sum — and refuses to tell Ontario taxpayers how much public money they're handing over to the world's richest person, citing a confidentiality clause that he could have negotiated away.

    As infrastructure minister, announced and signed the $100-million Starlink deal with SpaceX in late 2024 (Global News; The Canadian Press). As Treasury Board President she refused on September 24 and 25, 2026 to reveal the cancellation cost, saying "the people voted to cancel the contract" and that the SpaceX financials "are confidential and will remain so."

Bills

Promises (4)

Kept

Surma promised an interim Science Centre facility after closing the Don Mills site

“In the meantime, we are making every effort to avoid disruption to the public and help the Ontario Science Centre continue delivering on its mandate through an interim facility, as well as alternative programming options.”

· Ministry of Infrastructure news release

What happened · Jun 29, 2026

An interim Science Centre opened at Harbourfront Centre on June 29, 2026, about two years after the Don Mills closure.

The Science Centre's KidSpark space opened at Harbourfront Centre in December 2024, and a pop-up ran at CF Sherway Gardens until January 4, 2026. On December 10, 2025, Tourism Minister Stan Cho announced that an interim location would open at Harbourfront Centre 'by summer 2026'. On June 29, 2026 the province opened the first phase of the interim site. It said the site would cover about 86,000 square feet once fully running (the Don Mills building was about 568,000 square feet) and would operate until 2029.

Not yet due

Ford government said the new Ontario Place Science Centre could open as early as 2028

“Infrastructure Ontario will be releasing a Request for Proposals to help identify a temporary location for the Ontario Science Centre, while work continues to build a new permanent home for the Science Centre at Ontario Place with an opening slated for as early as 2028.”

Ministry of Infrastructure news release, · Ministry of Infrastructure news release

What happened · May 25, 2026

2028 hasn't arrived, but the government's own releases now say the new centre is on track to open in 2029.

In its December 3, 2024 Ontario Place audit, the Auditor General wrote that 'The new building is expected to open in 2029', using a date supplied by Infrastructure Ontario. On February 26, 2026 the province awarded the $1.04 billion construction contract and said the building would be finished 'as early as 2029'. On May 25, 2026 the province broke ground and said the facility 'is on track to open in 2029'. The province also says the interim Harbourfront Centre site will run until 2029.

Unclear

Surma said moving the Science Centre would save taxpayers $257 million

“The business case confirms that the relocation will save Ontario taxpayers $257 million over a 50-year period when compared to the cost of remaining at the current site and will also provide a greater share of space for programming than is the case at the current site.”

· Ministerial statement, Ontario Newsroom

What happened · Dec 3, 2024

The Auditor General found the relocation's estimated cost had risen $397 million (47%) to $1.444 billion by November 2023, but said the cost of staying would also have risen, without giving a figure.

The March 2023 business case put the cost of staying at Don Mills at $1.304 billion and the cost of moving to Ontario Place at $1.047 billion (both 50-year net present value), a gap of $257 million. On December 3, 2024 the Auditor General reported that 'As of November 2023, based on the latest available cost information, the total cost estimate for building and maintaining the new OSC at Ontario Place increased by $397 million (or 47%)... If these costs are added to the $1.047 billion above, the total is now $1.444 billion.' The Auditor added that 'costs of rehabilitating and remediating the existing OSC site would also have increased', without giving a figure. In February 2026 the province signed a fixed-price $1.04 billion contract to design, build, finance and maintain the new building, which is a different basis from the 50-year estimate.

Broken

Surma: Ontario Place plan includes 'an underground public parking facility'

“The plan also shows how the new, modernized Ontario Science Centre will be integrated with the preserved and upgraded Cinesphere and pod complex, as well as an underground public parking facility that will serve visitors across the site and will include increased spaces for bicycle parking.”

· Minister's statement, Ontario Newsroom

What happened · Jun 24, 2025

On June 24, 2025 the government announced a five-storey, above-ground parking structure on the waterfront in place of the underground facility.

Surma's September 14, 2023 statement presented an underground public parking facility as part of the updated plan; CTV reported in April 2023 that the plan was a five-storey underground garage, which Ford said the province would own. The Auditor General's December 3, 2024 report listed a five-level below-grade garage at the new Science Centre site at more than $1.3 billion. On June 24, 2025 the Premier's Office announced a publicly owned, above-ground structure of up to 3,500 spaces at the existing surface lot south of Lake Shore Boulevard. On June 11, 2026 the province awarded Pomerleau a $198 million contract for an 'open-to-air, above-ground, five-storey' garage.

Who benefited

Sources

↑↓ move↵ focus⌘↵ open page→ start a path from here